• Home
  • News
  • Politics
  • Business
  • Entertainment
  • Education
  • Interviews
  • Sports
Facebook X (Twitter) Instagram
Trending
  • ECOWAS: e-Commerce Can Raise W’African Trade to 35%, Boost Small Businesses
  • African Centre Demands Probe into Killing of Katsina Cleric
  • Insecurity: KACRAN Proposes 45-day Deadline to End Banditry in N’West, N’Central
  • APM Dissolves Bauchi Exco, Inaugurates Caretaker Committee 
  • Hakeem Bamgbola Donates Hilux Van to Itire-Ikate Campaign Council 
  • Abiodun Reassures Ijebuland on Awujale, Projects Economic Boom for Ogun East
  • Omoluorogbo Grammar School at 50: Aiyedatiwa to Commission Administrative Block, Flag Off Classroom Projects
  • Bauchi 2027: APC Candidate Won’t be Intimidated, Says Abubakar’s Camp 
Facebook X (Twitter) Instagram
The Gazelle NewsThe Gazelle News
  • Home
  • News
  • Politics
  • Business
  • Entertainment
  • Education
  • Interviews
  • Sports
The Gazelle NewsThe Gazelle News
Home » FG Fixes Q1 2024 To Complete Abuja-Kaduna Road Project
News

FG Fixes Q1 2024 To Complete Abuja-Kaduna Road Project

Khadijah OlowodeBy Khadijah OlowodeJuly 8, 2023No Comments12 Views
Facebook Twitter Pinterest LinkedIn WhatsApp Reddit Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email

By Abimbola Ogunnaike

The Federal Ministry of Works and Housing has fixed the first quarter of  2024  to complete the reconstruction work on the Abuja-Kaduna-Kano highway

The Permanent Secretary in the Ministry, Mahmuda Mamman, made this disclosure on Friday, July 7, 2023 during an inspection of the road and other ongoing federal road projects in Kaduna State.

Mamman took a tour of the 375.9 km of the dual carriageway way beginning from the Abuja end through Kaduna to Zaria and extending further to Kano all in the North-West zone.

During the inspection tour, the Permanent Secretary attributed the late completion of the road project which was awarded since 2017 to insecurity and funding challenges, which he said are being sorted out to ensure that the contractor delivers the project next year.

The essence of the inspection according to him is to assess the progress made so far by the contractor handling the Abuja-Kaduna-Zaria-Kano Road project, Messrs Julius Berger Nigeria Plc.

Among other challenges identified by Mamman and the project manager during the inspection are the issue of funding, insecurity, and weather conditions, which they noted had largely slowed down the project.

The Mamman also inspected the ongoing reconstruction work on the Kaduna Western bypass road, expressing disapproval of the slow pace of work by the contractor handling the project.

Abuja Complete FG Project Q1 Road
Share. Facebook Twitter Pinterest LinkedIn Tumblr Telegram Email
Khadijah Olowode

    Related Posts

    ECOWAS: e-Commerce Can Raise W’African Trade to 35%, Boost Small Businesses

    October 28, 2026

    African Centre Demands Probe into Killing of Katsina Cleric

    October 28, 2026

    Insecurity: KACRAN Proposes 45-day Deadline to End Banditry in N’West, N’Central

    October 28, 2026

    ECOWAS: e-Commerce Can Raise W’African Trade to 35%, Boost Small Businesses

    October 28, 2026

    African Centre Demands Probe into Killing of Katsina Cleric

    October 28, 2026

    Insecurity: KACRAN Proposes 45-day Deadline to End Banditry in N’West, N’Central

    October 28, 2026

    APM Dissolves Bauchi Exco, Inaugurates Caretaker Committee 

    October 28, 2026
    © 2026 All Rights Reserved. The Gazelle News. Designed By DeedsTech.

    Type above and press Enter to search. Press Esc to cancel.