  • Lagos Begins Pump Installation At Iju, Akute Water Stations To Boost Supply
  • Corruption Prosecution Over Unfunded Contracts, Tightens Grip on MDAs
  • LAWMA Academy Launches 2026 Summer School
  • World Breastfeeding Week: First Lady Oluremi Tinubu Urges Global Community to Commit to Advancing the Practice
  • Presidency Defends Tinubu’s Economic Reforms, Replies Atiku on Nigeria’s Reform Journey
  • Tragic: Singer Kefee’s Widower Loses Wife Two Weeks After Welcoming First Child
  • Insecurity, Herder Attacks Threaten Benue’s Status as Nigeria’s Food Basket — Official
  • FG Tasks NTAC on Public Diplomacy to Showcase Nigeria’s Foreign Policy Achievements
Facebook X (Twitter) Instagram
The Gazelle NewsThe Gazelle News
  • Home
  • News
  • Politics
  • Business
  • Entertainment
  • Education
  • Interviews
  • Sports
The Gazelle NewsThe Gazelle News
Home » NNPC Fulfils Promise, Delivers Port Harcourt Refinery; Achieves Mechanical Completion, Flare Start-up of Refinery’s Area 5 Plant
Life

NNPC Fulfils Promise, Delivers Port Harcourt Refinery; Achieves Mechanical Completion, Flare Start-up of Refinery’s Area 5 Plant

Khadijah OlowodeBy Khadijah OlowodeDecember 22, 2023No Comments15 Views
Facebook Twitter Pinterest LinkedIn WhatsApp Reddit Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email

The Nigerian National Petroleum Company (NNPC) Ltd. has fulfilled its pledge of achieving the mechanical completion of rehabilitation work on Area 5 Plant of the Port Harcourt Refining Company (PHRC).

Rehabilitation work has been ongoing at the Refinery for over two years and the NNPC Ltd. had pledged to complete Phase One of the project (mechanical completion and flare start-up) of Old Port Harcourt Refinery (Area 5) by 31st December 2023.

Speaking during an inspection tour of the rehabilitation project, which also coincided with the 15th Refineries’ Rehabilitation Steering Committee Meeting, the Group Chief Executive Officer, NNPC Ltd., Mr. Mele Kyari, said as of December 15th, 2023, 84.4% of Area 5 Plant, a key component of the Refinery, and 77.4% of the entire rehabilitation project have been completed.

“In our quest to ensure that this refinery is re-streamed to continue to deliver value to Nigerians, we made a promise that we will reach a mechanical completion of phase one of the rehabilitation project by the end of December and get the other plants running in 2024. Today, we have kept those commitments,” Kyari stated.

The GCEO commended the NNPC Ltd.’s staff and the EPCIC contractors for doing a great job in ensuring that the refinery achieved that significant milestone.

In his remarks, the Chairman of NNPC Ltd Board, Chief Pius Akinyelure described the milestone as “historic”, stressing that the board was proud of the staff and management of the refinery.

“We are just starting. We want to be at the highest level of production so that we will keep the prices of petroleum prices in the country stable in order to give comfort to our people and generate more revenue for our country,” Akinyelure noted.

Also speaking, the Minister of State for Petroleum Resources (Oil), Senator Heineken Lokpobiri, said the milestone is another landmark of the renewed hope agenda of President Bola Ahmed Tinubu, GCFR.

He thanked Nigerians for their patience and the trust they have in NNPC Ltd.’s ability to deliver on this huge project.

In his address, the Minister of State for Petroleum (Gas), Rt. Hon. Ekperikpe Ekpo, said re-streaming the Refinery will herald a good omen for the nation’s Liquefied Petroleum Gas (LPG) industry, as LPG, also known as cooking gas, is a major bye-product of the Refinery.

Also speaking, the Managing Director of Tecnimont Nig. Ltd., Fabio Del Cioppo, one of the EPC Contractors of the Rehabilitation Project, said his company remains committed to fulfilling the terms of the contract.

The PHRC rehabilitation project, which costs about $1.5bn, is an EPCIC project that covers Engineering, Procurement, Construction, Installation, and Commissioning phases. For Area 5, the Engineering, Procurement, Construction, and Installation have all been completed. The mechanical completion signifies the closure of the Construction and Installation phases.

More importantly, the milestone was achieved under an excellent Health, Safety and Environment (HSE) record, which stood at over 9.5 million manhours with zero Loss Time Injury (LTI).

Mechanical Completion NNPC Port Harcourt refinery
Share. Facebook Twitter Pinterest LinkedIn Tumblr Telegram Email
Khadijah Olowode

Related Posts

Lagos Begins Pump Installation At Iju, Akute Water Stations To Boost Supply

August 3, 2026

Corruption Prosecution Over Unfunded Contracts, Tightens Grip on MDAs

August 3, 2026

World Breastfeeding Week: First Lady Oluremi Tinubu Urges Global Community to Commit to Advancing the Practice

August 3, 2026

Lagos Begins Pump Installation At Iju, Akute Water Stations To Boost Supply

August 3, 2026

Corruption Prosecution Over Unfunded Contracts, Tightens Grip on MDAs

August 3, 2026

LAWMA Academy Launches 2026 Summer School

August 3, 2026

World Breastfeeding Week: First Lady Oluremi Tinubu Urges Global Community to Commit to Advancing the Practice

August 3, 2026
© 2026 All Rights Reserved. The Gazelle News. Designed By DeedsTech.

Type above and press Enter to search. Press Esc to cancel.